Construction kickoff
May 20-June 5, 2022
You are here
Stage 1
June 2022-January 2023
Build west side of 209th Avenue between Alexander and Eggert streets.
Build eastbound right turn lane on Blanton Street at 209th Avenue.
Construct waterline improvements on Tualatin Valley Highway at night.
Temporarily widen south side of TV Highway.
Build north side of Alexander Street east of 209th Avenue.
Stage 2
January 2023-April 2023
Build curbs and sidewalk on the north side of TV Highway.
Build east side of 209th Avenue north of TV Highway.
Stage 3
April 2023-April 2024
30-day road closure to build 209th Avenue north of TV Highway.
Rebuild westbound lanes on TV Highway.
Build east side of 209th Avenue, south of TV Highway.
Stage 4
April 2024-June 2024
Build center lanes on TV Highway.
Only right turns allowed at the 209th Avenue and TV Highway intersection.
Stage 5
June 2024-August 2024
90-day road closure to reconstruct the south side of TV Highway and railroad crossing.
Stage 6
September 2024
Final paving and striping at night.