This open house was active from May 20-June 5, 2022. Information on this website may no longer be current. Email us for more information.
Construction dates are estimates and subject to change.
-
Construction kickoff
May 20-June 5, 2022You are here
-
Stage 1
June 2022-January 2023- Build west side of 209th Avenue between Alexander and Eggert streets.
- Build eastbound right turn lane on Blanton Street at 209th Avenue.
- Construct waterline improvements on Tualatin Valley Highway at night.
- Temporarily widen south side of TV Highway.
- Build north side of Alexander Street east of 209th Avenue.
-
Stage 2
January 2023-April 2023- Build curbs and sidewalk on the north side of TV Highway.
- Build east side of 209th Avenue north of TV Highway.
-
Stage 3
April 2023-April 2024- 30-day road closure to build 209th Avenue north of TV Highway.
- Rebuild westbound lanes on TV Highway.
- Build east side of 209th Avenue, south of TV Highway.
-
Stage 4
April 2024-June 2024- Build center lanes on TV Highway.
- Only right turns allowed at the 209th Avenue and TV Highway intersection.
-
Stage 5
June 2024-August 2024- 90-day road closure to reconstruct the south side of TV Highway and railroad crossing.
-
Stage 6
September 2024- Final paving and striping at night.